The Exhibition Planning Process in 6 Stages: From Brief and 3D Proposal to Move-In and Move-Out
Updated: Oct 16
By Chris | Vision Design
Exhibition planning does not start with drawing. It starts from the organizer's deadlines and works backward. Every stage has information the exhibitor needs to provide and work we need to deliver, and if either side runs late, the stages after it get squeezed.
This article goes through the 6 stages in order: what you need to prepare, what we deliver, and where things most often get stuck. How to set goals and choose a booth type is covered in "How to Plan a Booth," so we will not repeat it here.
Key points:Plan backward from the organizer's deadlines; the latest step decides when you need to start. We recommend starting 3 months before the show.
The Exhibition Planning Process at a Glance: 6 Stages
The process has 6 stages: brief, 3D proposal, final design and construction drawings, organizer review, graphics and fabrication, and move-in through move-out.
Each stage has two tracks: the information the exhibitor provides, and what we deliver. The chart below puts both side by side, so you can see which step you are on.

Stage 1: Confirm the Brief and Constraints (3 Months Before the Show)
This stage is about collecting the constraints, so the design has clear boundaries to work within.
What the exhibitor provides:
Exhibition goals
Budget range
Booth location and number of standard booths
Exhibit list and dimensions
Logo in vector format
On our side, we read the exhibitor manual and venue regulations first and pull out the constraints: height limits, over-height applications, and power. If these are not clear at the start, even a beautiful design can be sent back at review.
For how to set goals and choose a booth type, see "How to Plan a Booth": How to Plan a Booth.
Stage 2: 3D Proposal and Revisions
Agree on the direction first, then spend time on details.
At the proposal stage, we produce 3D views quickly so you can see the direction and proportions: where the entrance is, how high the logo sits, how the display and meeting areas are divided. Changes are fast at this stage, so if the overall direction raises questions, we adjust on the spot.
Only once the direction is set do we develop details and materials. Do it the other way around and you spend time on a direction that is not yet decided; the more detail you add, the more likely you are to start over.
At this stage, the exhibitor provides feedback and decisions: which direction, and what to adjust. We deliver the 3D proposal and a new version after each round of changes.

Stage 3: Final Design, Build Method, Quote, and Construction Drawings
Once the design is final, we decide the build method first, then draw.
There are two routes, custom-built and modular system, each suited to different situations. For the differences, see "Custom-Built or Modular System Booth?": Custom-Built or Modular System Booth?Once the build method is set, we can quote.
When the quote is confirmed, we start the construction drawings. Our drawings go down to one page per display cabinet: plan, elevation, side section, and a 3D view, with grooves and angles all marked.
Construction drawings are the shared reference for the build crew and the print shop.Carpenters build from them, and the print shop checks graphic sizes against them. Both work from the same set of drawings, which is why we draw in this much detail.
Stage 4: Organizer Review and Forms (About 1 Month Before Move-In)
The review submission is the least flexible deadline in the whole process.
Taking the technical regulations for Taipei Nangang Exhibition Center Halls 1 and 2 (Aug 2026 edition) as an example:
Booth design drawings: submitted for review 30 days before move-in
Documents for over-height or two-story booths: 15 days before the show
Power applications through the official electrical contractor: submitted to the venue 15 days before move-in
Organizer forms: most close about one month before move-in
On height: anything 4 m or above counts as over-height and needs a separate application, up to a maximum of 6 m. For details, see "Building a Booth at Taipei Nangang Exhibition Center": Building a Booth at Taipei Nangang Exhibition Center.
The booth contractor prepares the drawings and the exhibitor (the space holder) stamps them with its company seal. The exhibitor's job is to check and stamp the drawings; we deliver the complete drawing set and all the forms. If the drawings do not pass review, revise and resubmit quickly rather than waiting until the last day. For how to prepare the review documents, see "What to Submit for Organizer Review": What to Submit for Organizer Review.
Stage 5: Graphics Production and Fabrication
Graphic sizes follow the construction drawings, and what goes on each surface is checked against the 3D, one face at a time.
Backdrops, lightboxes, and wall graphics are not sized by eye. They follow the graphic-size drawing in the construction set. We then check what goes on each surface against the 3D, so nothing ends up on the wrong face or out of sync with the content.
The exhibitor provides the logo and key visual files, in vector format please. Screenshots blur when enlarged, and we do not enlarge screenshots that contain text.
Before files go to the print shop, all text is converted to outlines so missing fonts on their side cannot shift the layout. For steps that are easy to get wrong, such as cut-out lettering, we prepare extra material so there is room to redo it.

Stage 6: Move-In, Show Days, and Move-Out
We move in during the organizer's assigned time slot and check the booth on site against the construction drawings.
After move-in, we check item by item against the drawings: whether the logo is fully visible (cut off or hidden behind a corner does not count), every dimension, and the position of the electrical box. All of this is settled before the show opens.

When the show ends, we dismantle the booth and restore the space within the organizer's move-out window. Afterward, the construction drawings and as-built photos are filed together so they can be reused next time. With a modular system, the components can be reused as well.
Where the Process Most Often Gets Stuck: 4 Practical Reminders
1. Change one dimension, and four places have to change with it.
The construction drawings, the 3D, the graphic files, and the graphics order sheet are all linked by the same dimensions. Changing sizes after the design is final costs the most, so confirm dimensions carefully in the earlier stages.

2. Logo and key visual files arrive late, or only as screenshots.
Graphics come late in the sequence. If files arrive late or the quality is not good enough, the schedule gets compressed. Please provide the logo as a vector file in Stage 1.
3. Review submission pushed to the deadline.
Drawings that fail review need revising and resubmitting. Submit on the last day and there is no time left to resubmit. Submit early and leave room to revise after a rejection.
4. Drawing starts before the goals are set.
Without focused goals, the design keeps changing direction. Set the goals first; see step one of "How to Plan a Booth."
FAQ
Q1: How far ahead should exhibition planning start?
We recommend 3 months before the show. Organizer forms usually close about one month before move-in. Booths that need over-height or two-story structures should start earlier.
Q2: Can we hire you for 3D design or construction drawings only?
Yes. We take on design-only and drawings-only projects, and we can also take a project from 3D proposal and construction drawings all the way through to the on-site build.
Q3: Who prepares the review documents?
The booth contractor prepares the drawings, and the exhibitor (the space holder) stamps them with its company seal.
Q4: Can interactive installations and AV be planned together with the booth?
Yes. The installations are produced by partner vendors, and we integrate them into the booth's floor plan, power, and circulation.
Q5: What should the exhibitor prepare at the start?
Exhibition goals, budget range, booth location and number of standard booths, exhibit list and dimensions, and a vector logo file.
Related Projects
Automation Taipei 2026 joint booth
SEMICON Taiwan 2026
CYBERSEC 2026
Compact booth projects: modular system booths from 2 to 4 standard booths
Related services: Custom-Built Booth Design & Build, Modular System Booth Planning & Build, Portfolio
Further reading: How to Plan a Booth, Planning a Multi-Brand Joint Booth, Custom-Built or Modular System Booth?, What to Submit for Organizer Review, Building a Booth at Taipei Nangang Exhibition Center, Choosing an Exhibition Design Company